· 10nd February 2005 - RTSL visited the school and had preliminary discussion with Principal & Vice Principal. New land was offered for reconstruction of school. RTSL visited the proposed land. It was found to be marshy land with over 6 feet of land filling and filled land settlement of months, probably years before school foundation could be built. The delay and cost of the filling the land was unfavourable conditions. RTSL rejected the proposed land and informed to the MOE.
|
|
|
 |