Progress So Far...
Mahamaya Balika Vidyalaya.
Hikkaduwa, Galle District.


23rd May 2006 - On 19th April 2006 - quotations were called for clearing and leveling the land. Three quotations were received and the lowest bidder M/s P&J Construction was awarded the contract on 21st April 2006. Work began immediately and on clearing the bushes and the trees levels were marked for cutting the earth and leveling the land. Enclosed are pictures taken on 23rd May 2006 on the work in progress

 

 


 

 

Cutting the Earth

More earth cutting.

   
   

Excess earth moved away.

A tough task with many trucks transporting the earth

   

 

 

A huge slope and much more earth to excavate

The top section still remains to cleared of Bushes and Trees

   
   
 

View from the center of the Land to the main road entrance

 
   
   

 
 
 
Designed & Developed by Four Corners Lanka (Pvt) Ltd